// Chapter 22.1 · PLC · What Is a PLC

What Is a PLC: CPU, Memory, I/O, the Scan Cycle, Scan Time, the IEC 61131 Standard and Choosing a PLC

In 1968 General Motors' Hydra-Matic transmission plant wanted to stop rewiring relay panels every time the car models changed. That brief produced the first PLC (the Modicon 084). The core idea is unchanged today: a computer built to survive the factory floor, which reads inputs from switches and sensors, decides with a program an electrician can read, and drives outputs — repeating predictably, without end.

By Ajarn ModUpdated
In 30 seconds
  • PLC = power supply + CPU + memory + I/O modules + communication ports
  • One scan: read inputs into the image → run the program top to bottom → write outputs → system tasks
  • Typical scan time 1–20 ms · worst-case response ≈ input delay + 2 scans + output delay
  • Its strength is robustness and deterministic behaviour, not speed

PLC architecture Basic

PSU24 VDCCPUProgram · dataTimers · countersComm portsDIDOPush-buttons · selectorsLimit switchesPNP/NPN proximityOverload contacts4–20 mA transmittersContactor coilsLamps · sirensSolenoid valvesVFD commands4–20 mA control valveHMI · SCADA · programmerInputs → decide by program → outputs
Figure 1 · The PLC sits between two groups of field devices: those that “tell” (buttons, sensors) and those that “do” (contactors, valves, lamps)
PartFunctionWhat to know
Power supplyConverts 230 VAC to 24 VDC for the CPU and I/OUse a separate supply for high-current field loads (solenoids)
CPURuns the program, manages I/O and communicationLook at speed per instruction, memory size and special functions (PID, fast counters)
MemoryStores the program, data and settingsRetentive data keeps its value through a power failure (battery/flash)
Digital I/O0/1 signals from switches and to coils24 VDC sinking/sourcing, relay/transistor outputs
Analog I/OContinuous 4–20 mA, 0–10 V signals12–16-bit resolution, must be scaled to engineering units
CommunicationTalks to HMIs, SCADA, drives and other PLCsEthernet (PROFINET, EtherNet/IP, Modbus TCP), RS-485 (Modbus RTU)

The scan cycle Intermediate

A PLC does not “watch” its inputs continuously. At the start of each scan it takes a snapshot of every input terminal into the input image table, then runs the program rung by rung from top to bottom, reading from that snapshot. Coil results are written to the output image, which is sent to the output terminals all at once at the end of the scan. Working this way means input values cannot change part-way through a scan, so the result is predictable.

1 Read inputsterminals → I image2 Run programtop → bottom, left → right3 Write outputsQ image → terminals4 Housekeepingcomms · self-test1 scanWorst case ≈ 2 × scan + input filter01234I0.0I imageQ0.0scans → · a mid-scan change is seen next scan
Figure 2 · Right: button I0.0 changes in the middle of scan 0, is read into the image at the start of scan 1, and output Q0.0 changes at the end of scan 1 (seen at the terminal in scan 2)

F1 Scan time

tscan=tread I+tprogram+twrite Q+tcomm/diagt_{scan} = t_{read\,I} + t_{program} + t_{write\,Q} + t_{comm/diag}

F2 Program execution estimate

tprogram≈Nbit tbit+Nword tword+Nreal trealt_{program} \approx N_{bit}\,t_{bit} + N_{word}\,t_{word} + N_{real}\,t_{real}

F3 System response time

tin+tscan+tout  ≤  tresp  ≤  tin+2 tscan+toutt_{in} + t_{scan} + t_{out} \;\le\; t_{resp} \;\le\; t_{in} + 2\,t_{scan} + t_{out}

F4 Shortest pulse surely seen

tpulse>tscan+tint_{pulse} > t_{scan} + t_{in}
Example F-1

A conveyor runs at 1.2 m/s; 30 mm parts pass a photoelectric sensor; PLC scan 10 ms, input filter 3 ms

  1. Time the part blocks the sensor: t=0.030/1.2=25t = 0.030/1.2 = 25 ms

  2. F4: must exceed 10+3=1310 + 3 = 13 ms → 25 ms is caught ✓ (almost a 2× margin)

  3. If the conveyor speeds up to 3 m/s: t=10t = 10 ms < 13 ms → parts may be missed; use a high-speed input or a hardware counter

  4. F3: the time from a part reaching the sensor to the air-jet reject (transistor output 0.1 ms + solenoid 15 ms) is at worst ≈ 3 + 20 + 0.1 + 15 = 38 ms → the part travels 46 mm in that time, so mount the air nozzle this far beyond the sensor

Types of PLC Basic

TypeCharacteristicsGood for
Nano/Compact (all-in-one)CPU and I/O in one housing, 10–60 points, limited expansionSingle machines, pumps, building services
Modular (rack)Choose the CPU, I/O and communication modules as needed, hundreds to thousands of pointsProduction lines, process plants
Safety PLCDual CPUs, self-checking, SIL/PL certifiedEmergency stops, light curtains, safety gates, burner management
PAC / IPC (soft PLC)An industrial computer running an IEC 61131-3 runtimeHeavy computation, multi-axis motion, large data volumes
Smart relayProgrammable relay with a small display and function blocksVery small jobs, replacing a few relays

PLC compared with relays and microcontrollers

CriterionRelay panelPLCMicrocontroller
Changing the logicRewireEdit the programEdit the program (written in C)
Industrial robustnessHighHigh (IEC 61131-2 tests for EMC, temperature, vibration)User must design it in
DiagnosticsMeasure point by pointOnline status view, event logsDepends on the programmer
PredictabilityHighHigh (fixed scan, watchdog)Depends on the design
Cost per pointLow for very small jobsModerateVery low

The IEC 61131 standard Intermediate

IEC 61131 makes PLC knowledge transferable across brands. The parts electricians and engineers use most:

  • Part 2 (equipment): 24 VDC input Types 1/2/3, ON/OFF voltage ranges, EMC tests — details in I/O wiring
  • Part 3 (languages): LD, FBD, ST, SFC (and IL, deprecated in the 2013 edition), data types, standard timers and counters — see IEC 61131-3 languages

How to choose a PLC Intermediate

F5 I/O count with spare

NI/O=⌈1.2 Nrequired⌉(15–25 % spare)N_{I/O} = \left\lceil 1.2\,N_{required} \right\rceil \quad (\text{15–25 \% spare})
  1. Make an I/O list: count digital and analog inputs and outputs and high-speed inputs, with their types (PNP/NPN, 4–20 mA)
  2. The required response time (F3) and special functions (PID, counters, motion)
  3. Communication with the HMIs, drives and SCADA systems already in the plant
  4. Safety: is a safety PLC or safety relay needed?
  5. Environment: panel temperature, humidity, vibration
  6. Plant standards and spares on hand — a brand the maintenance staff already know is often better value than a cheaper one

Frequently asked questions

If a button is pressed for less than the scan time, will the PLC see it?

Possibly not. Inputs are read once at the start of each scan, so a pulse shorter than the scan time plus the input filter time can appear and disappear between two reads. Fast signals (encoders, high-speed part-counting sensors) need high-speed inputs, hardware counters or interrupts.

Why does writing the same coil in two places make the program misbehave?

Because the PLC executes from top to bottom, the value written by the lower coil overwrites the value from the upper one before the outputs are sent at the end of the scan. The upper coil appears not to work (double-coil syndrome). Combine the conditions into a single rung, or use SET/RESET deliberately.